NBN Co's RFS dates are increasingly accurate

Since the election, NBN Co has consistently been providing expected ready for service dates that are more accurate than ever before (for areas less than three months from expected Ready for Service). These dates are now more realistic and achievable target dates — now that the company is without the pressures of the election and that some contractual disputes are resolved and Telstra has resumed remediating pits.

From the data below, only 10 FSAMs of the 30 FSAMs were delayed from the last expected ready for service dates provided by NBN Co. Of the 10, only 2 were delayed over 15 days — with the highest being 23 days off (2CFS-06).

Many other areas were on time or ahead of schedule. 6MSP-01 and 7BEV-01 were "brought forward" by over a month, perhaps due to contractual uncertainty being resolved in Tassie and construction work chugged along at full speed in WA.

This is great news for all parties involved: NBN Co, Access Seekers (and RSPs), consumers and of course, the Government. It does appear indeed that NBN Co is asserting more stability and certainty in their forward projections. Now that they're getting increasingly accurate, I call for NBN Co to start publishing these monthly reports publicly… instead of us having to siphon the information off Telstra's Wholesale website :)

Expected RFS dates from Nov, Dec, Jan and Feb vs Actual RFS

FSAM RFS* Dates Actual RFS* Date Diff (from last RFS)^
Nov '13 Dec '13 Jan '13 Feb '13
2BLK-01 08 Nov '13 15 Nov '13 +7 days
4MKY-02 15 Dec '13 15 Nov '13 on time
3BRA-02 15 Nov '13 15 Nov '13 on time
3CTN-07 08 Nov '13 20 Nov '13 +12 days
2SAW-04 05 Dec '13 29 Nov '13 -6 days
4GUL-05 27 Nov '13 29 Nov '13 +2 days
2BLK-04 21 Nov '13 06 Dec '13 +15 days
2BLK-02 21 Nov '13 06 Dec '13 +15 days
2CFS-06 13 Nov '13 06 Dec '13 +23 days
3BRU-04 09 Dec '13 11 Dec '13 11 Dec '13 on time
6GLT-01 05 Dec '13 20 Dec '13 13 Dec '13 -7 days
4GUL-04 20 Dec '13 31 Jan '14 20 Dec '13 -20 days
6MSP-01 Feb '14 17 Jan '14 20 Dec '13 -34 days
8CSU-02 22 Jan '14 27 Dec '13 27 Dec '13 on time
2RCH-01 30 Nov '13 31 Jan '14 10 Jan '14 -21 days
2CFS-07 21 Jan '14 07 Feb '14 17 Jan '14 -21 days
5SFD-04 05 Dec '13 20 Jan '14 17 Jan '14 -3 days
6APP-02 10 Feb '14 12 Feb '14 17 Jan '14 +5 days
2DAP-02 11 Jan '14 05 Feb '14 20 Jan '14 -16 days
3BRU-06 04 Dec '13 30 Jan '14 30 Jan '14 31 Jan '14 +1 day
2LID-03 20 Dec '13 12 Feb '14 23 Jan '14 05 Feb '14 +13 days
6MDR-02 20 Jan '14 08 Feb '14 08 Feb '14 05 Feb '14 -3 days
4CAI-03 Mar '14 25 Feb '14 25 Feb '14 07 Feb '14 -18 days
6GLT-02 21 Jan '14 08 Feb '14 08 Feb '14 07 Feb '14 -1 day
7BEV-01 22 Jan '14 30 Mar '14 30 Mar '14 12 Feb '14 -46 days
6MDR-03 09 Dec '13 07 Feb '14 07 Feb '14 12 Feb '14 +5 days
3BRA-01 31 Jan '14 16 Jan '14 04 Feb '14 27 Feb '14 14 Feb '14 -13 days
3TMN-02 13 Jan '14 15 Feb '14 15 Feb '14 14 Feb '14 14 Feb '14 on time
6MSP-02 Jun '14 08 Feb '14 08 Feb '14 14 Feb '14 14 Feb '14 on time
6GLT-03 14 Jan '14 15 Feb '14 06 Mar '14 28 Feb '14 28 Feb '14 on time

* RFS — ready for service, declared when 90% of premises within an FSAM are passed but not necessarily serviceable
^ — difference is calculated between the last provided RFS date and the actual RFS date. +ve dates indicate delays, -ve dates indicate "ahead of schedule"


Sorry, no match for the embedded content.

Old Comments

Add a New Comment
or Sign in as Wikidot user
(will not be published)
- +

Add a New Comment

Unless otherwise stated, all of the site's contents (including articles, blog post and code snippets) is:
Copyright © Kenneth Tsang 2014